  • 软考题目-软件设计师英文题目,卧槽怎么选一个错一个

    2019-08-09

    英语自认为还算可以,不好也不差。但是做软考英文题目题,选一个错一个啊。备受打击。

    题目如下:

    A project is a [temporary] 【temporary:临时的】(Sequence) of unique 【unique:独特的】,complex,and connected activities having one goal or purpose and that must be completed by a specific【specific:具体的】 time,

    within budget【预算】,and according to (Specifications).【specifications:规范

    Project management is the process of scoping【范围】,planning,staffing,organizing,directing,and controlling the development of a(n) ( acceptable)【可接受的】 system at a minimum cost within a specified tiem frame.

    For any systems development project,effective project management is necessary to ensure that the project meets the (deadline)【工期,结束日期】,is developed within an acceptable budget,and fullfills customer expectations and specifications .Project management is a process that starts at the beginning of a project,extends through a project and doesn't culminate【最终导致】 until the project is completed.

    The prerequisite【先决条件】 for good project management is a well-defined system development process.Process management is an ongoing activity that documents ,manages the use of ,and imporves an organization's chosen methodology【方法】(the process) for system development.Process management is  concerned with the activities,delierables,and quality standards to be applied to ( all )【所有】 project(s).

  • 相关阅读:
    UVA
    题目1008:最短路径问题
    怎样使用安卓变声电话软件实现边变声边通话
    Map接口及其子类
    oracle slient静默安装并配置数据库及仅安装数据库不配置数据库shell
    oracle db_unnqiue_name db_name sid_name instance_name service_name
    oracle 配置监听
    oralce dubugs
    sqlplus conn远程连接
    centos 修改shm
  • 原文地址:https://www.cnblogs.com/hamish26/p/11328350.html
Copyright © 2011-2022 走看看